IP-Projects Statusportal

de en

> Traffic Switch - FRA11 Location

  • Type: Service
  • Category: Computing Centre / Network
  • Start: 2026-04-09T15:00:00+0000
  • End: 2026-04-09T16:40:00+0000
On Thursday, April 9, 2026, we are planning a system changeover at the FRA11 site at 5:00 PM. This involves optimizing the traffic path and preparing for the deprovisioning of the remaining Juniper switches.

Traffic to the FRA4 and FRA1 sites will be rerouted to a direct connection between the edge switch and the backhaul switch to eliminate the previous detour via the Juniper switches.

Due to the migration, packet loss may occur for a few seconds for traffic exchanged via the carriers at the FRA11 site.

Update: Maintenance work is ongoing

2026-04-09 15:37
Maintenance work is currently still underway; we plan to complete it by 18:00 MESZ

Update: Maintance completed

2026-04-09 16:58
Maintenance was successfully completed at 6:40 p.m.Due to a formatting error, there was a disruption affecting the 134.255.244.0/24 prefix for approximately 10 minutes, and there was also an interruption in our VLAN transport services. We apologize for the inconvenience.