IP-Projects Statusportal

de en

> Powermaintenance nLighten Datacenter

  • Type: Service
  • Category: Computing Centre / Network
  • Start: 2026-07-11T07:00:00+0000
  • End: 2026-07-11T16:00:00+0000 (expected)
On Saturday, July 11, 2026, our data center service provider nLighten will be performing power maintenance at the FRA4 site between 9:00 a.m. and 6:00 p.m. 
We have received the following information from nLighten regarding the maintenance:
“We must switch the power supply for the existing RPPs (power switchgear) in order to perform work on the low-voltage switchgear.
During the switchover, only one power supply will be available, resulting in reduced redundancy.
To carry out the work, one power supply must be shut down for 8 hours; this work will take place on a Saturday.”

Although deactivating individual power feeds poses a high risk, it should not disrupt the availability of our services. To minimize potential risks, IP-Projects is implementing the following preventive measures:
-  Visual inspection of all server systems with redundant power supplies to ensure that both power supplies are correctly connected to the power feeds.
- Visual inspection of the automatic transfer switches on servers that have only one power connection—redundant power supply for MS servers.
The inspections will be conducted according to the dual-control principle. At the time of maintenance, we will have technicians on-site on standby to restore services as quickly as possible in the event of a disruption.